OCR Text |
Show GOLDFIELD COMPANY EMPLOYS 125 MEN One hundred and twenty-five men are employed In the mines and mill of the Goldfleld Development company In preparing pre-paring for the starting of the bis project on September 1, which, according to latest reports, is about the date the 1200-ton mill will start, says the Ooldtleld Tribune. Trib-une. Nino thousand tons of ore are broken In the Red Top, and as soon as this has been removed the tlrlny of blasts bringing down from 3000 to 6000 tons of ore will be resumed. The undersround work in the Combination Combina-tion and January claims 1ms practically been completed, the head frame at the Development shaft has been erected, the machinery is in place, and construction of the 500-ton ore bin is well under way. |