OCR Text |
Show Stillwater dam bid $3 million under estimate Seventeen firms have entered bids for construction of the Upper Stillwater Dam Foundation Excavation at the Bureau of Reclamation office in Duchesne. The apparent low bidder is Tutor-Saligo-Mittry, Encino, Calif., with a bid of $5,864,600 compared with the engineer's estimate of $8,911,350. Bids ranged up to $13,058,000. The location of the site is about 45 miles northwest of Duchesne in Rock Creek Canyon, near the Rock Creek Ranch and I-odge. The dam project is part of the Bonneville Unit of the Central Utah Project. The work will include the diversion of Rock Creek through the dam foundation, foun-dation, excavation of materials above the rock foundation, clean-up ol rock foundation for inspection; and construction con-struction of roads, work areas, and , stockpiles for future contracts. Construction time, under terms of the specifications, is G20 calendar days. |