OCR Text |
Show Construction Claim Rejected by Price PRICE A claim of a Spanish Fork contracting company for payment pay-ment of $5109.10 allegedly due on a contract for installing a new municipal mu-nicipal water line had been rejected Tuesday by the city council The council said a settlement had already been made under the original orig-inal agreement and threatened a counterclaim of $25,000 on the grounds portion of the system were improperly installed and required reconstruction. The firm seeking the payment is the E. K Ferguson A Sons company. com-pany. The contract for rebuilding the line was awarded by the council on November 5, 1S35, in the sum of S33.672.ft6. The claim of the company now tinder consideration is based on a contract clause which Mr. Ferguson said provided the oity would pay for extra work and materials not specified speci-fied in the contract. |