OCR Text |
Show Water project half completed ENTERPRISE -Construction on the City water improvement project is currently about half completed. Most of the main lines have been finished, and the work on the First North line, is about to the half-way point, according to City officials. The Winsor subdivision line has been completed and also the pipe has been laid on the Black Hill. A six-inch line has also been installed to the Clove subdivision. Mayor Lyle Jones stated that work hasn't begun yet on several laterals, and work on the spring boxes ynust be done. The estimated finish date for the work is in mid-January, but the contractor and the City of Enterprise have agreed that completion will depend upon weather conditions. |