Show commissary BUILDING work on the commissary building has proceeded very slowly the past ten days A large inflow 0 seepage water has been the main obstacle to overcome and until the present time no effective method of removing it has been adopted A large hand pump which proved inadequate although run night and day has been replaced by a steam driven force pump and woric from now on will ba more effective the first forms were set up which will be filled with concrete saturday september ast 1st la tha date set for the completion of tha building but owing to delays some weeks will pass away before it la ready tor occupation work on the remodeling 0 the de pot la expected to start some time in august |