OCR Text |
Show Telluride Improves Milford Service A step in the direction of betterment bet-terment and improvement of service was taken early Tues day morning at Milford when Tellulride Power Co. crews installed in-stalled automatic reclosing circuit cir-cuit breakers on the Milford City and South Milford irrigation irriga-tion substations, and several sets of sectionalizing disconnect switches on the distribution lines. During the last week a construction con-struction crew completed all possible preliminary work, and during a 1 - hour 47-minute power shutdown, Tuesday morning, morn-ing, completed the installation. Other improvements for the Beaver County portion of the Telluride system are planned, officials announced, and will be completed as rapidly as material ma-terial is received. |