Show Track Laying on Sugarville Line Track laying on the Sugarville branch is progressing very slowly and Wednesday had reached -a point two miles north of the turn west of Delta as near as we could learn. This makes about six and one-half miles of track laid sto far. The road is being balasted as the steel is being laid and, judging from the progress now being made it will be "three or four weeks yet before track laying lay-ing reaches Sugarville. Supt. VanHousen and Engineer Brown were here the latter part of last week looking over the new work. |