OCR Text |
Show R Y BE R GS GET CONTRACT. Moran's Bid Is Lower, but Time Limit Is Longer. Special to The Tribune PROVO, Sept 16 Ryberg Brothers of Salt lake were tonight avnrded the contract con-tract for non-retnforced pacing on '"enter Mrvel and to additional hlocka In other parts of the city for 3n.C20.:i. the work to be finished in severity days. Prior to the awarding if the contract P. J, Moran, with his attorney. W. .1. Rarrette. appeared ap-peared before the eity l ornmtssloners and dJaettaaet with them the bade for paving, srhlrh it had been officially announced would he swarded to Hybera Rrothers. Mr. MOTOO'l hid ftir the nnii-rlnforced psvlne) on Center street was SIM71 64. and Ryberg Brothers, the next lowest bidder1, ws ItO.fll.gf, I Mr. Rarrette gave some rea-ns why the contract should be awarded to Mr. Moran. the principal reason being the low bid put in by him. and he slated further that Provu '-oulil not ffoid to let It go out that Provo would not piny fair with contractors. |