OCR Text |
Show Will Not Delay Work. Special to The Tribune. OGDEN. Aug. 29. With an order placed for tho additional steel which will be required to extend the present eight-story eight-story structure, it Is estimated by the general engineer that construction work on the addition to the Eccles building will be under way within six weoks. The order calls for the delivery of the steel In this city within that time. Fred M. Nye, who gave up a long lease In ordor that the new building might be extended, will vacate his present quarters quar-ters by September 10. The work of removing re-moving tho two-story brick structure will bo started at once to make way for the olght-story Bteel skyscraper. As the Nye building has a. deep basement, the contractor con-tractor declares that very little excavation excava-tion will be nocossary for the addition. |