Show WORK ON THE MALAD BRANCH IS PUSHED Grading on the Short Line's Malad ! Valley branch. Is progressing rapidly. The branch will' run from Corinne to the sugar company's plant a distance of about sixteen miles. . About five miles of this distance has already been graded grad-ed and the rest of It will be graded In about thirty days. , . The laying of the track, it Is estimated, estimat-ed, .will take about two weeks longer. As to when the branch will be built pn to Malad, about twenty-four miles further up the valley, has not been decided. de-cided. ... The Short Line also commenced work today on a three-mile spur track from the main line In Idaho to the new beet sugar factory at Idaho Falls. This will be completed within a short time. ' |