OCR Text |
Show NEW CITY POWER LINE IS NEAR COMPLETION A new power line from the Strawberry Water Users Association Assoc-iation power ralant at tht mouth of ! Spanish Fork Canyon to the substation sub-station on Fourth South Street will be completed within the next few week; it was announced Thursday by the city engineer's office. The project has been awaiting the completion of legal proceedings proceed-ings for the right-of-way. The new line will increase the feed voltage from 11,000 to 44,000. That will mean an increase capacity cap-acity in town from 900 kilowatts to 1500 kilowatts. Following the hook-up of the line to three new transformers, overloading of the present transformer trans-former capacity will be done away with. It will mean possibl-ities possibl-ities of better service and a more efficient power supply, even during dur-ing peak hours. |