Show Work Progressing On New Highway Work is rapidly advancing on the eight-mile construction project on U. S. Highway 40 between Myton and reports Wallace J. resident engineer for the Utah State Road Commission at Under terms of the contract with L. A. Young Construction of Richfield and the Vernal Sand and Gravel of construction was to have begun March Time limit of the contract was working days from that Completion date of the project is expected to be by Items of work include a plant mix asphalt surfacing and construction of one new concrete bridge along this mile Prior to the March 1 contract starting grade work had been commenced and irrigation structures were being including the placing of a to replace an overhead |