Show CONTRACTOR WAITING FOR ARRIVAL OF ASPHALT Contractor George A. Heman ha3 completed the laying of the concrete baao on Twenty-fifth street, betwe'en Washington and Wall, and on Wall, between Twenty-fourth and Twenty-flfih. Twenty-flfih. and Is prepared to surface with asphalt as soon as the material ar-ries ar-ries He Is also ready to surface Hudson avenue, between Twenty-third Twenty-third and Twenty-fourth streets Mr Heman stated this morning (hat he is much disappointed over the delay in the transportation of the material from California and that had the asphalt been shipped when or dered all the work would have been done r.t this time. He sas that he ordered the asphalt In July, but that as it was of a superior quality, as required re-quired in the plans and specifications, longer time was necessary In the making mak-ing of it. However, the shipment was reported to hae been made a number of days ago, but the material bas not yet arrived. oo |