OCR Text |
Show logan-cache a ik tort rids opening' postponed I The extending of the opening of bids for construction on the Logan-Cache Airport project to December 19, has been done to allow for a change in specifications specifica-tions of the plans. Originally the project called for the gravel for the airport to be delivered by yardage and has been changed to require it to be delivered by weight. A number of contractors have bid on the project already ana more bids are expected. Much of the gravel hauling for the airport runways will be done during the winter months while the ground is frozen. Meanwhile, work on the new highway adjacent to the airport has already gotten underway. The fence for the south line of the highway is being constructed ana work has begun on the road by Carl E. Nelson, contractors. |