Show Duchesne school construction work progresses on schedule Work on the two school building projects at Duchesne are ahead of the construction schedule of the states Thomas J. Aplanalp of the Duchesne County School WORK WAS commenced in shortly after the contracts were on both the gymnasium at the high school and the groundwork for the elementary school The brick work on the gym- matching brick veneer over cinder block is nearly reports Jack projects representative for the Duchesne County Board of and buildings supervisors for the architects of the two The painters are at work on the interior of the THIS WEEK the elementary school building is being and the laying of the brick veneer walls A light tan brick veneer with a rose-tinged mortar is being j Target date for the completion of the Duchesne high school gymnasium is in mid-October just in time for the teams to start practicing for the basketball Cannon Mullen of Salt Lake City are architects for this and the contractor is and Gammon Construction of who is doing the construction of this masonry and steel under a Benny Mitchell of Salt Lake formerly of the Upalco is the contractor for the brick laying for the THIS GYMNASIUM construction is the second phase of the enlargement project of the Duchesne high that was started seven years It attaches onto the north end of the school building and connects with the main school In planning for this the and dressing rooms were built in the section constructed seven years Mr Fitzwater said the gymnasium Is almost like the Altamont high school It lias dividing door with a folding-sliding door divider that will allow for two A small team room is built onto the back of the TO THE FRONT the facilities built in include rest rooms for the a serving kitchen for the students to use to serve refreshments to the and a big The gymnasium is designed with two large double doors and two single all on the front The heating system from the existing school building Is being extended into the A WET HEATING is being Installed at the elementary W. Salt Lake is the architect for this The contractor is Turner Construction Company of Salt Amount of the contract awarded is with a construction period It is hoped to have the elementary school done the first of the a few weeks ahead of the March completion date Abplanalp NEW SCHOOLS RISE Wor cSer ml a ill verj- well on the gymnasium of JJ elementary and the bottom photo T he i e all f the brick work U nc The are anea Contractor building now going up- on both |