Show PIPELINE WORK IS NOW UNDER WAY work on the pipeline started on the salt lake devils slide end ten men from morgan starting to work last monday morning it itis is stated that the wage is 60 cents per hour eight hours constituting a days work and 40 hours a weeks work operators of trench machines and helpers are working three shifts the editor Is informed that the trench machine Is capable of adli digging a mile ot of trench in eight hours if not too rocky the pipe will be laid at a depth of about two feet we are informed that the pipeline misses evanston wyo by about a mile and a halt half to the south from evanston it parallels the utah power light co power line to devils slide the williams construction st co has the contract from oasis to the slide work on most sections of the mile pipe line from fort laramie to the salt lake city refinery was reported under way and it is stated more than men will be employed when the peak of construction st is reached |