Show 16 BIDDING ON DEER CREEK With bids to be opened February Febru-ary 10th for award of Deer Creek project construction units;, some 16 contractors are busily engaged engag-ed in reviewing plans and specifications specifi-cations for estimate preparation reports Chief Engineer E. O. Larson Lar-son of the project. Scooped up imemdiately after thei'r arrival from U. S. Reclamation Reclama-tion bureau headquarters in Denver Den-ver were available plans and specifications by the eager contractors. con-tractors. Many of the group figuring figur-ing on dam development have already al-ready reviewed ground conditions. Bids include building of the dam itself, railroad relocation from the damsite to Charleston, and highway detour. In the dam will go 2,700,000 cubic yards of earth and the bulk of 18.000 cubic yards of concrete. Steel reinforcement will weigh 1,910,000 pounds. Contractors furnish labor and supervision with the U. S. put-chasing put-chasing most of the material. |