Show WORK BEGINS : ON REPAIRING WATER SYSTEM The C. L. Wheeler Construction company of Salt Lake who awarded the contract by the Springville Spring-ville city council last fall for tne installing of the new cast iron pipe nnd repairing of the city water work system of Springville began construction work Monday morning of this week. The pipe was purchased by the city and has been arrivin all during dur-ing the winter months1, and has been distributed to the various streets of the city where it is to be laid. The line along the west side of Main street was the section selected select-ed for the beginning of the operation. opera-tion. According to specifications the main trunk line from the head house to Main street and the mnin street line will be instnlled first. Then the smaller lines on the west side of the city. |