Show THREE SHIFTS OF MEN AT WORK ON ROOSEVELT FT DUCHESNE HIGHWAY three shifts of men are working at the gravel pit on ward hill crushing and hauling gravel for base material to be laid on the section of highway now under construction st between here and ft duchesne before spreading the asphalt surface the asphalt is mined and ready for hauling but will not be laid until about the middle of july samuel owens resident engineer said approximately 70 men are working on the project and it is expected to be completed near the first of august |