Show Work Resumed on New High School After more than two months de lay on account of the severe winter wint-er weather, work has been started again on the new high school building build-ing at Coppertou. The weather has been so cold all winter that it was iinsafe to go on with the masonry and all work on the buildings was Mispended, A large force of men were put to work there the first ;f tiie week and it Is not likely at this time of year that any further de lays will occur on account of the weather. . The superstructure of the main building will lie completed withiu about thirty days It is expected and also the foundations of the audi torium and the gymnasium will be ready for the brick work to commence com-mence on them. All work Is to be comleted ou the new plant within six months or by September first, according to the contract, so that school may open iu'the new build-lug build-lug this fall. |