OCR Text |
Show I NEW UNIT FOR SLC MILLS Erection of Additional Grain Elevator to Start Early Next Year Plans for an additional grain elevator ele-vator for the Globe Grain & Milling company are now fa the hands of architect, ar-chitect, according to J 11. Waugh, construction engineer of the company The new storage structure will have a capacity of MJO.fiOft bushels giving the company a total of 1,250,000 bushels bush-els when the new unit Is completed. Work on the new structure Will be started during the enrh pari of 1921 the building to he of concrete construction con-struction and to cort $ 160,000. It will be equipped with twent;. largo grain tanks and 12 small grain tanks. The pouring of the second floor slab in the mill will be started next week with two plft working until the pouring Is completed, according to Bnginber Waugh, The work on the . mill is being rushed to completion. |