Show OF MOAB HIGHWAY MAKING RAPID PROGRESS oil processing of the federal aid highway through moab town commenced the last of the week and a crew operating under the direction of district engineer R A gulls of the state highway commission Is making rapid progress with the work the oiling started at the loveridge ranch the south terminal of the highway and the work will have been completed through main street by the last of the week avem vem oilman of price Is the foreman in charge the moab garage company has the contract for hauling the oil in from thompsons Thomp sons two tank trucks one with a capacity of 1750 gallons and the other gallons are being operated day and night with two shifts and the oiling Is proceeding 24 hours a day the oil Is heated at thompsons Thomp sons |