Show BUILDING POWER LINE TO THE KNIGHT SMELTER A part of the material for the line which the Telluride Power company compano will run from Eureka to the Tintic smelter arrived during the week w ek and the remain remainder remainder remainder der which includes the poles and wire should be received in a day or two says the Eureka Reporter H C Don Carlos and John F Rowe who have charge of the Telluride com affairs In Tintic state that the four Cour and a half miles of line can be completed com completed completed within ten days da s or two weeks The smelting company will put up a substation at the smelter and will have it itin itIn itin in readiness by b the time that the power company is ready to turn on the current |