Show WORKERS ON STREET PROJECT DRIVE DRIVEWAY WAY construction curb and gutter along the four blocks on the east cast side of main street is SO 80 per cent completed at present cliff angus supervisor reported today remaining work on this side of the street consists of driveways and will take about 10 days for completion after which work on th the t asphalt s sidewalks ide walks will bs be started mr angus said curb and gutter construction will bo be started on the west side of main street on october 1st ast alt angus belic believes ves |