Show j Home road is ready for project pushed The oil mat surface on the mile road project from Home junction to Mt Home is in the reports E. J. resident engineer at Duchesne for the Utah State Road Commission This is the on the second phage of this tri-project road construction miles from Bluebell to The third road on this contract to Nelson Bros Construction Co of Salt Lake 2 miles from Altamont to is receiving the base course gravel now preparatory to applying the oil Resumption of the surfacing work on the Home and roads is contingent with the weather and other Possibly the chip seal coat will be applied later Wilson The Altamont to Altonah stretch will receive the surface course gravel oil mat then it will be ready for the Work was started on the contract for the three projects July The contract has working days to complete the Extremely cold weather then caused the road construction work to be stopped for several months this past w inter |