Show Antelope Road Repairs Repairing of the Antelope Island Road which was washed out in May due to high winds and waves on the Great Salt began earlier this THE CONTRACT for the work was given to L. A. Young and a Richfield The work is expected to cost around The public information director for the Utah Road Clark said that work was to start a week earlier but was delayed until this week because the contractor had to replace his superintendent who died a few hours before the project to THE COMPANY has 35 working days to complete the repair work and it should tc completed sometime around Following the storm in the road was closed while emergency repairs were Six to eight feet of material was washed out on both sides of the In some places large holes in the road were made driving After the temporary the road was then opened to the public until permanent repairs could be DURING THE reconstruction people visiting the island can expect delays and in some cases may be asked to turn back while the repairs are The work is being done through the Ogden District of the Utah Department of |