Show Water Sewer Projects 30 P Pit Pel t. t Done COALVILLE COALVILLE- According to the latest engineers engineers engineers engi engi- estimates the water and sewer collection projects under construction in Coalville are in excess of thirty per cent com com- In a report submitted to the Housing and Home Administration tion and the City Council of Coalville Coal Coal- vine ville e the engineers figures show the time elapsed as 13 per cent I 1 construction completed as over 30 per cent This according to I Mr Art V. V Maxwell Is showing the entire project running way ahead of schedule Working Every Day Christensen Construction Company Company Company Com Com- pany Salt Lake City prime contractor con con- tractor f for r the coll collection system system- ha has been working every da throughout the winter However Mr Duane Christensen en president informed the city inspectors on the job jab that it may be necessary to close down operation for a few days until the cold wave has passed as the frost froat is now being I driven into the ground to a depth of over 18 IS Inches and the terrible I strain and stress s on his hla equipment equipment equip equip- I ment is showing up in the form of breakdowns in linkage lines I Mr Lloyd Crittenden subcontractor sub con I tractor on the water sY system tem has completed nearly 50 60 per cent of the line construction however due to the freezing of the terrain by old man winter has closed down his operation until spring i are reminded that an Up Crews will be in operation operation operation op op- during spring time as soon as the frost is out of the earth enough for good and backfilling Until this time II everyone Involved is asked to be bea a little patient as the frozen I earth Is hard to put back into as asgood asgood I good a condition as prior to construction construction con con- time and there will necessarily be a time of settling and movement caused by the frozen ground I City Inspectors The city inspectors assigned to the project have met with officials officials of ot- and request all property owners owner to be anti anticipating on the location of their connection tees I well in advance They report that I I most lines have been staked on I the streets and request t all aU property property prop prop- erty owners to check them and to be ready to Inform the Inspectors inspectors inspectors tors where they would like to have their connection made prior to actual construction on the I 1 trench line In front of their prop prop- erty This will enable the tion department and the contractor tor to do a much better job of installation when the time comes for tor running the laterals I |