OCR Text |
Show UU TWENTY MEN ON WEBER RIVER BRIDGE The Midland Bridge company ha3 a force ol about twenty men on the joint city and Bambcrgei bridge across Weber river It will be fully six weeks before the concrete abutments and center pier uie completed. Th' two end abutments abut-ments have been practically finished and the concreters are busy with the pier In the center of the river. Just when the bridge will be ready lor use cannot be stated, as much steel construction must be dom- a1 ter the concrete abutments and pit?rs have been erected. Construction ha3 been alow on this job as the company was Interrupted in Its work with high water In the spring of the year, and since that time the water has been so high that conylructlon has been at a disadvantage. |