Show Work Goes Ahead "Satisfactory" progress on construction con-struction of the new 100 by 120 foot, Logan-Cache airport hangar was reported today by Erwin U. Moser, city engineer, who estimated esti-mated that the structure will be completed in about one month. Walls were in place on all sides to the tops of the building's windows or 13 feet high today, he said. Ceiling of the hangar will be 22 feet high. The structure was scheduled for completion about October 10, he explained, but delays in obtaining priorities will interrupt the schedule sched-ule somewhat. Work conducted so far has been done with non-critical non-critical materials and materials reclaimed from other structures. Ace S. Raymond of Logan is contractor on the project which is being financed by $10,000 given by the state through the state aeronautics commission by $13,417 aptropriated by Cache county and Losan city. |