Show tooele thoele smelter resumes after long shut shutdown down r blowing in of the first furnace a copper took place oa on thursday at the tooele thoele plant of the international smelting company As it will take from ten days to two weeks to warm up the furnace no attempt will be made to charge tha th furnace until june 12 to 15 capa city operation will be possible about july 1 about june 16 15 fires will be built under two lead blast furnaces in ascue asmuth as the construction of lead I 1 fu furnaces permits more rapid heat ing the lead leaa department of the smelter will be ready to undertake capacity reduction of ores and con cen about twenty tour four hours after blowing in all old employees holding eions on july 1 1921 will be given their old positions providing they ap p py for work within ten days aate after r their departments start operations |