Show Power Company Installing Another Diesel Desel Unit To ro keep up with the steadily increasing demand for electrical electric electric- al energy at Moab Moat th the Utah Power Light company has commenced the Installation of another diesel power unit at it atts Its ts local plant The new engino eh- eh en- en gino the fourth diesel unit atthe at athe the he Moab plant In addition to tots its ts hydro hydra plant will generate 45 of power giving the Moab plant a maximum output of close to killo watts according to Mars Pope l local al manager of the company Demand for tor electrical energy has practically doubled at Moab during the past two or three years Installation of the new diesel unit has made n necessary essary the instruction construction o of a larger building build build- ing ng at the power plant work on which Is now under way It will take about two months to complete complete com corn pleto the improvements Mr Pope ope states |