Show Oar Car Tracks Delay f East Paving Work on the paving of ot Seventh East should be completed within six weeks Commissioner Commissioner- o of ot Streets Sheets I P. P J. J Moran said Tuesday morning The project which was scheduled by contract to be finished by July 24 has been delayed by the laying of street car tracks Mr Mor Moran n s said ld Temporary tracks had to be laid while the new permanent tracks were being p put t In In and this ne necessarily es- es delayed the paving which could not be done until the tracks were Installed he said The tracks must set et 21 days before any weight is put upon them The firm of Gibbons and Reed which have the contract will not b be required to pay the 25 a d day y forfeit forfeit for for- feit Mr Moran said as they are Inno inno In Inno no way to blame for the delayed work |