Show PROGRESS OF WORK ON THE LARGE BUILDINGS Steel construction for the front of tho Alhambra theatre building has been completed and concrete men are busy tilling in between the steel on the interior Brick men are finishing the side walls, and terra cotta and stone masons are engaged on the front part of the theatre. There are 1 yet some heavy girders to be placed over the stage of the playhouse. The concrete tloor for the balcony 16 being! laid Between the theatre building and ! the Dee-Eccles social-business block I ou Twenty-fourth street, there Is an excavation for the central heating plant, which will supply heat for the two structures and the Colonel Hudson Hud-son building. Progress is being made on the Dee-Ecc)e8 Dee-Ecc)e8 block. Heavy steel for the roof has been placed in position and carpenters are now removing the fcrius which support the concrete floor of the second story. |