Show W. 15. COON GETS THE SIDE WALK JOB Bids for the construction of approximately ap-proximately three miles of cement side walk were opened last Thursday Thurs-day evening at the regular meeting of the Town board, and the contract was let to W. B. Coon for $11,771. Several bids were submitted to the board for their consideration, and a great variation of figures were shown. The bids: were as follows: Fotheringham & Robinson ..$13,341 Pitchforth & Mathews 17,000 Martin, Martin and Markman 13,400 Gillespie, Kenyon & Johnson 14,975 W. B. Coon I 11,771 D. I. Frazer .12,871 Heuser Packard: Co .16,7 00 Mr. Coon is getting material ready rea-dy and a crew of men lined up, and will start work next Monday, with the intention of having the job done by the first of August. |