OCR Text |
Show Rio Algom. 4 Offices Re-Situated Moab offices of Rio Algom Corporation were moved to the mine and mill site of the company in Lisbon Valley last Friday prior to an expected ex-pected opening date of the mill sometime in April. The company experienced some delays in the mining section of their work when they struck an underground water source last summer. The mill operation, however has continued on schedule, and mine development has been pushed to keep pace. Normal operations in the production shaft should begin sometime this month, with stockpiling of uranium ore until the mill becomes operable oper-able in late March or April. The company has been building up its salaried work force during the past twa months with hiring expected to accelerate now until the company attains the maxi-' mum force after the mil is in full operation. |